Product Description
The ABB REK510 is a current injection device designed for rotor earth-fault protection of synchronous machines. It is used with the excitation circuit of generators and other synchronous machines to help detect insulation faults between the rotor field winding and earth. The REK510 applies a 100 VAC secondary voltage to the rotor circuit through coupling capacitors, producing a small measurement current that can be monitored by the associated earth-fault protection function. ABB identifies REK510 as an injection device rather than a general-purpose controller unit.
Product Parameters
| Item | Specification |
|---|---|
| Brand | ABB |
| Model | REK510 / REK 510 |
| Product Type | Current Injection Device |
| Application | Rotor Earth-Fault Protection |
| Protected Equipment | Synchronous Machine / Generator Rotor |
| System | Excitation Circuit |
| Injection Voltage | 100 VAC secondary voltage |
| Auxiliary Supply | 58, 100 or 230 VAC, 50/60 Hz |
| Injection Method | Coupling Capacitors |
| Installation | Surface-Mounted Metal Enclosure |
| Dimensions | Approx. 140 × 266 × 257 mm |
| Weight | Approx. 5.4 kg |
| Protection Function | Rotor Field-to-Earth Fault Detection |
| Status | Legacy / Existing-System Protection Component |
| Condition | Verify actual stock condition before installation |
FAQ
Q: What is the ABB REK510?
A: REK510 is a current injection device used for earth-fault protection of the rotor excitation circuit in synchronous machines.
Q: Is REK510 a controller unit?
A: ABB documentation identifies it specifically as a current injection device, not a general-purpose controller. It works together with the associated rotor earth-fault protection function.
Q: What voltage does REK510 inject into the rotor circuit?
A: The device establishes a 100 VAC secondary voltage through coupling capacitors toward the rotor circuit and earth.
Q: What auxiliary supply can the REK510 use?
A: ABB documentation specifies secured 58 VAC, 100 VAC, or 230 VAC supplies at 50/60 Hz, depending on the configured application.
Q: What should be checked before replacement?
A: Verify the complete REK510 variant, auxiliary supply voltage, connection arrangement, coupling capacitors, associated protection relay, and original generator excitation-system configuration before installation.
Recommended ABB Models
- ABB REK510-AA | Current Injection Device
- ABB REG630 | Generator Protection and Control IED
- ABB REM543 | Machine Protection Terminal
- ABB REM545 | Machine Protection Terminal
- ABB REX640 | Protection and Control IED
- ABB REG615 | Generator and Interconnection Protection
- ABB REG670 | Generator Protection and Control IED
- ABB REG650 | Generator Protection and Control IED
- ABB RET630 | Transformer Protection and Control IED
- ABB PCM600 | Protection and Control IED Manager